Basics
FX EAM uses Crafts to track the cost of labor on work order tasks.
|
While FX EAM generates accounting detail for the parts on work orders, it does not generate accounting transaction detail for labor. |
Key Features
-
Each Craft has a name and a Planned Labor Rate.
-
Crafts tie to Work Tasks, not directly to Work Orders. A single Work Order may have different Crafts assigned to different Work Tasks.
-
Create a craft for each labor rate.
-
The craft’s labor is reflected in the costs of work orders and preventative maintenance reports based on the rate and the number of hours worked.
|
Work Tasks without a craft use the default labor rate defined in Custom Settings. |